Question: Activity EXP COST EXP % COMPLETE ACTUAL % COMPLETE ACTUAL COST TO DATE site prep 3.0M 85 90 2M pour concrete 8.0M 75 80 9M
| Activity | EXP COST | EXP % COMPLETE | ACTUAL % COMPLETE | ACTUAL COST TO DATE |
|---|---|---|---|---|
| site prep | 3.0M | 85 | 90 | 2M |
| pour concrete | 8.0M | 75 | 80 | 9M |
| Construction | 10.0M | 60 | 70 | 6M |
1. the scheduled variance is?
2. the scheduled performance index is?
3. the cost performance is?