Question: Activity EXP COST EXP % COMPLETE ACTUAL % COMPLETE ACTUAL COST TO DATE site prep 3.0M 85 90 2M pour concrete 8.0M 75 80 9M

Activity EXP COST EXP % COMPLETE ACTUAL % COMPLETE

ACTUAL COST TO DATE

site prep 3.0M 85 90 2M
pour concrete 8.0M 75 80 9M
Construction 10.0M 60 70 6M

1. the scheduled variance is?

2. the scheduled performance index is?

3. the cost performance is?