Question: Activity Expected Time EST LST Total Budgeted Cost A 2 0 0 $10,000 B 2 0 1 $12,000 C 3 2 3 $15,000 D 4
Activity Expected Time EST LST Total Budgeted Cost A 2 0 0 $10,000 B 2 0 1 $12,000 C 3 2 3 $15,000 D 4 3 3 $24,000 Activity B is 15% complete and $1,000 has been spent on the activity, the cost difference implies a cost __________. problem underrun overrun deficiency