Question: Activity Expected Time Standard Deviation of Time Estimate Immediate Predecessor(s) A 7 2 - B 3 1 A C 9 3 A D 4 1

Activity

Expected Time

Standard Deviation of Time Estimate

Immediate Predecessor(s)

A

7

2

-

B

3

1

A

C

9

3

A

D

4

1

B, C

E

5

1

B, C

F

8

2

E

G

8

1

D, F

H

6

2

G

a) Find the critical path and project completion time.

b) Find the probability that the project will take more than 49 time periods to complete.