Question: Activity Expected Time Standard Deviation of Time Estimate Immediate Predecessor(s) A 7 2 - B 3 1 A C 9 3 A D 4 1
| Activity | Expected Time | Standard Deviation of Time Estimate | Immediate Predecessor(s) |
| A | 7 | 2 | - |
| B | 3 | 1 | A |
| C | 9 | 3 | A |
| D | 4 | 1 | B, C |
| E | 5 | 1 | B, C |
| F | 8 | 2 | E |
| G | 8 | 1 | D, F |
| H | 6 | 2 | G |
a) Find the critical path and project completion time.
b) Find the probability that the project will take more than 49 time periods to complete.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
