Question: Activity Expected time (t) Variance A 6 0.11 B 6 0.81 3 2.24 D 7 0.63 E 7 0.92 F 13 0.08 G 5 1.05

Activity Expected time (t) Variance A 6 0.11 B 6

Activity Expected time (t) Variance A 6 0.11 B 6 0.81 3 2.24 D 7 0.63 E 7 0.92 F 13 0.08 G 5 1.05 H 2 1.72 Consider the path A-B-D-F-H of the project given in the table ablve. a) What is the completion time for this path? b) What is the standard deviation of this path? Round your answer to 4 decimal places. c) What is the probability the project will be completed within the due date of 35 days? Round your answer to 4 decimal places. d) If you want to be 97% confident of completing the project ontime what should be the due date? Round your answer to 1 decimal place