Question: Activity immediate predecesor time A - 5 B A 4 C A 2 D A 2 E B 7 F C 5 G E,F 9
| Activity | immediate predecesor | time |
| A | - | 5 |
| B | A | 4 |
| C | A | 2 |
| D | A | 2 |
| E | B | 7 |
| F | C | 5 |
| G | E,F | 9 |
| H | F | 4 |
| I | D,G,H | 6 |
Please Calculate the Es, Ef, Ls, Lf and slack time for each activity