Question: Activity Immediate Predecessor Normal time Normal Cost (FD) Crashing Time Crashing Cost (FD) A - 3 150 3 150 B - 4 200 3 220
Activity Immediate Predecessor Normal time Normal Cost (FD) Crashing Time Crashing Cost (FD) A - 3 150 3 150 B - 4 200 3 220 C A 4 500 3 575 D A,B 5 300 3 400 E C,D 5 400 4 550 F E,D 3 200 2 600
- Draw the AON diagramme for the above schedule.
- Calculate crash cost per day for each activity
- What is the estimated completion time?
- What is the best option to crash the project to complete in 1 day earlier?
- What are the best options to crash the project to complete in 2 days earlier?
- What are the best options to crash the project to complete in 3 days earlier?
What are the best options to crash the project to complete in 4 days earlier?