Question: Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A None 4 8 10 B A 2 8 24 C A 8 12 16

Activity

Immediate Predecessor

Optimistic Time

Most Likely Time

Pessimistic Time

A

None

4

8

10

B

A

2

8

24

C

A

8

12

16

D

A

4

6

10

E

B

1

2

3

F

E, C

6

8

20

G

E, C

2

3

4

H

F

2

2

2

I

F

6

6

6

J

D, G, H

4

6

12

K

I, J

2

2

3

What activities are on the critical path?

What is the total project duration using just the "most likely" times and the CPM method? (1 point)