Question: Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A None 4 8 10 B A 2 8 24 C A 8 12 16
| Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | None | 4 | 8 | 10 |
| B | A | 2 | 8 | 24 |
| C | A | 8 | 12 | 16 |
| D | A | 4 | 6 | 10 |
| E | B | 1 | 2 | 3 |
| F | E, C | 6 | 8 | 20 |
| G | E, C | 2 | 3 | 4 |
| H | F | 2 | 2 | 2 |
| I | F | 6 | 6 | 6 |
| J | D, G, H | 4 | 6 | 12 |
| K | I, J | 2 | 2 | 3 |
What activities are on the critical path?
What is the total project duration using just the "most likely" times and the CPM method? (1 point)