Question: Activity Immediate Predecessor ( s ) Time ( weeks ) Activity Immediate Predecessor ( s ) Time ( weeks ) A - 1 E B

Activity
Immediate Predecessor(s)
Time (weeks)
Activity
Immediate Predecessor(s)
Time (weeks)
A -1 E B 2 B -4 F C, E 7 C A 1 G D 2 D B 5 H F, G 3
The following represent activities in ABC Construction Company project.
A) Construct a network diagram?
b) The critical path is____?
c) The length of the critical path is___weeks?
Activity Immediate Predecessor ( s ) Time ( weeks