Question: Activity Immediate Predecessor Time in Days None 5 B A 2 02 A 7 D Band C 6 6 E 15 F B 9 G

Activity Immediate Predecessor Time in Days None
Activity Immediate Predecessor Time in Days None 5 B A 2 02 A 7 D Band C 6 6 E 15 F B 9 G 30 H D,E,F G 10 The above table is a simple project listing 8 activities and their respective time estimates: Using the Single Time Estimate CPM procedure, what are all of the activities that are not on critical path? Select one: B,C,D,E,F None of the choices are correct C,D,E,G CD OB, D, F, G Clear my choice