Question: Activity Immediate Predecessor Time (weeks) A Prepare Requirements Spec -- 06 B Prepare Design Spec -- 08 C Prepare Development Team A, B 12 D
|
6.1. Develop a PERT network for the project [14]
6.2. Identify the critical path. [02]
6.3. Determine the total project duration. [02]
6.4. Identify three activities that can be delayed and for each, determine the slack. [03]