Question: Activity Immediate Predecessor Time (weeks) A Prepare Requirements Spec -- 06 B Prepare Design Spec -- 08 C Prepare Development Team A, B 12 D

Activity Immediate Predecessor Time (weeks)

A Prepare Requirements Spec -- 06

B Prepare Design Spec -- 08

C Prepare Development Team A, B 12

D Develop & Test Module 1 C 04

E Develop & Test Module 2 C 06

F Develop & Test Module 3 D, E 15

G Conduct Comprehensive Sys Test E 12

H Refine & Hand Over System F, G 08

6.1. Develop a PERT network for the project [14]

6.2. Identify the critical path. [02]

6.3. Determine the total project duration. [02]

6.4. Identify three activities that can be delayed and for each, determine the slack. [03]