Question: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) G E , F 7 a . What is the critical path ( SHOW YOUR DIAGRAM AND CALCULATIONS

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
G
E,F
7
a. What is the critical path (SHOW YOUR DIAGRAM AND CALCULATIONS)?
The critical path is A-C-D-F-G
b. How many weeks will it take to complete the project?
The project completion time: A-C-D-F-G=24.
c. How much slack does activity B have?
Slack activity B has 11 Slack.