Question: Activity Immediate Predecessors Duration A - 2 B - 4 C - 4 D A 2 E B, C, D 2 F A 4 G
Activity Immediate Predecessors Duration A - 2 B - 4 C - 4 D A 2 E B, C, D 2 F A 4 G C, D 1 d) If you would have a chance to reduce the duration of two activities by one time unit each, which two activities would you choose? Will you be able to reduce this way the total project time?