Question: Activity Immediate Predecessors Optimistic (weeks) Most Likely (weeks) Pessimistic (Weeks) A 3 4 5 B A 4 5 12 C 2 4 6 D C

Activity Immediate Predecessors Optimistic (weeks) Most Likely (weeks) Pessimistic (Weeks)
A 3 4 5
B A 4 5 12
C 2 4 6
D C 3 4 5
E B, D 1 2 3
F E 2 4 6
G B, D 6 7 14
H G 6 8 10
I F, H 3 4 5

How do I find:

ES

EF

LS

LF

Slack

Critical path

The earliest time to start the project in order to have a .95 probability that the project will be done on time