Question: Activity Immediate Predecessors Optimistic (weeks) Most Likely (weeks) Pessimistic (Weeks) A 3 4 5 B A 4 5 12 C 2 4 6 D C
| Activity | Immediate Predecessors | Optimistic (weeks) | Most Likely (weeks) | Pessimistic (Weeks) |
| A | 3 | 4 | 5 | |
| B | A | 4 | 5 | 12 |
| C | 2 | 4 | 6 | |
| D | C | 3 | 4 | 5 |
| E | B, D | 1 | 2 | 3 |
| F | E | 2 | 4 | 6 |
| G | B, D | 6 | 7 | 14 |
| H | G | 6 | 8 | 10 |
| I | F, H | 3 | 4 | 5 |
How do I find:
ES
EF
LS
LF
Slack
Critical path
The earliest time to start the project in order to have a .95 probability that the project will be done on time