Question: Activity Immediate Predecessors Time A - 3 B A 1 C A 2 D B , C 3 E C 5 F C 3 G

Activity Immediate Predecessors Time
A -3
B A 1
C A 2
D B, C 3
E C 5
F C 3
G E 7
H E, F 5
I D, G, H 8
What is the critical path(s) and expected completion time for this project?
What activity has the largest amount of slack?