Question: Activity Immediate Predecessors Times (days) a m b A. Identify faculty and their schedules 4 6 8 B. Arrange transport to base 5 8 15
| Activity | Immediate Predecessors | Times (days) | ||
| a | m | b | ||
| A. Identify faculty and their schedules | 4 | 6 | 8 | |
| B. Arrange transport to base | 5 | 8 | 15 | |
| C. Identify and collect training materials | 2 | 7 | 7 | |
| D. Arrange accommodations | A | 1 | 2 | 4 |
| E. Identify team | A | 5 | 7 | 9 |
| F. Bring in team | B, E | 10 | 10 | 18 |
| G. Transport faculty to base | A, B | 3 | 4 | 7 |
| H. Print program material | C | 2 | 2 | 3 |
| I. Have program material delivered | H | 10 | 12 | 14 |
| J. Conduct training program | D, F, G, I | 6 | 8 | 18 |
| K. Perform fieldwork training | J | 5 | 5 | 5 |
What is the Early Start, Early Finish, Late Start, and Late Finish?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock