Question: Activity Immediate Predecessors Times (days) a m b A. Identify faculty and their schedules 4 6 8 B. Arrange transport to base 5 8 15

Activity Immediate Predecessors Times (days)
a m b
A. Identify faculty and their schedules 4 6 8
B. Arrange transport to base 5 8 15
C. Identify and collect training materials 2 7 7
D. Arrange accommodations A 1 2 4
E. Identify team A 5 7 9
F. Bring in team B, E 10 10 18
G. Transport faculty to base A, B 3 4 7
H. Print program material C 2 2 3
I. Have program material delivered H 10 12 14
J. Conduct training program D, F, G, I 6 8 18
K. Perform fieldwork training J 5 5 5

What is the Early Start, Early Finish, Late Start, and Late Finish?