Activity Initial node. Final node Estimated Duration (Days) A 1 2 2 B 2 3 3 C
Question:
Activity Initial node. Final node Estimated Duration (Days)
A 1 2 2
B 2 3 3
C 2 4 3
D 2 5 2
E 3 6 4
F 4 6 3
G 5 7 6
H 6 8 2
I 7 8 3
J 8 9 4
K 7 10 5
L 7 11 2
M 10 9 3
N 9 12 3
O 10 13 3
P 11 13 7
What is the critical path for this project and how long is it?