Question: Activity Name Predecessor Activity Activity Duration A - 4 B - 3 C A,B 7 D B 2 E C,D 5 F C,D 3 G
| Activity Name | Predecessor Activity | Activity Duration |
| A | - | 4 |
| B | - | 3 |
| C | A,B | 7 |
| D | B | 2 |
| E | C,D | 5 |
| F | C,D | 3 |
| G | E | 2 |
| H | F,G | 9 |
a. (2 Points) Prepare an AON Network Diagram. b. (4 Points) Identify all possible paths. Provide that information in a table. The heading of your table should as follows:
| Path | Duration |
c. (10 Points) Perform a forward pass and a backward pass. Display your results in an AON diagram. Use the following legend for your node(s).
| Activity | ES | EF |
| Duration | LS | LF |
d. (2 Points) Prepare a table summarizing the results of your Activity Schedule. The heading of your table should as follows:
| Activity Name | ES | EF | LS | LF | Slack |
e. (2 Points) Identify the critical path. What is the project duration?