Question: Activity # Normal # Crash # Normal # Crash # Slack Name Time Time Cost Cost Time A 1 5 1 5 4 5 0

Activity # Normal # Crash # Normal # Crash # Slack
Name Time Time Cost Cost Time
A 1515450045002
B 2619560062000
C 3325520062002
D 2323400040000
E 1919560056001
The table shows normal time, crash time, normal cost, crash cost and slack time of activities in a project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity. Ex: A)