Question: Activity Normal Duration Minimum Duration Crash Cost ($/day) A B C D E F G H I J 10 1 9 3 13 23 2
|
Activity | Normal Duration | Minimum Duration | Crash Cost ($/day) |
| A B C D E F G H I J | 10 1 9 3 13 23 2 3 2 2 | 8 1 5 3 12 21 1 2 1 1 | 50 - 25 - 165 60 150 150 210 100 |
f) The customer for whom the pool and bathhouse are being installed would like the project to be completed as swiftly as possible. As an incentive, the customer has offered to pay Bakersfield Pools an extra $250 for each day they can reduce the length of the project. Use the table above for crash cost and minimum duration information. What is the most economic duration of the project? How much extra profit would this generate for BP?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
