Question: Activity Normal duration (weeks) Immediate predecessors # weeks that can be saved by crashing Extra cost to crash ($/week saved) A 5 - na na

Activity

Normal duration (weeks)

Immediate predecessors # weeks that can be saved by crashing Extra cost to crash ($/week saved)
A 5 - na na
B 7 - 1 $1000
C 8 A 2 $600
D 9 A,B 3 $1500
E 10 B 2 $800
F 10 C,D 4 $2000
G 6 D 2 $1800
H 8 E na na

What is the minimum number of weeks required to complete this project without crashing any of the activities?

How many weeks of slack does task A have?