Question: Activity Normal time ( day ) Crash time ( days ) Normal cost Crash cost Predecessor A 8 6 $ 1 , 0 0 0
Activity Normal time day Crash time days
Normal cost
Crash cost Predecessor
A $ $
B $ $
C $ $ A
D $ $ A B
E $ $ C D
Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?