Question: Activity Normal Time (days) Crash Time (days) Normal Cost ($) Crash Cost ($) A 4 3 2000 2600 B 2 1 2200 2800 C 3
| Activity | Normal Time (days) | Crash Time (days) | Normal Cost ($) | Crash Cost ($) | |
| A | 4 | 3 | 2000 | 2600 | |
| B | 2 | 1 | 2200 | 2800 | |
| C | 3 | 3 | 500 | 500 | |
| D | 8 | 4 | 2300 | 2600 | |
| E | 6 | 3 | 900 | 1200 | |
| F | 3 | 2 | 3000 | 4200 | |
| G | 4 | 2 | 1400 | 200 |
- Identify the critical path. How much time will it take to complete the project?
|
- If you wished to reduce the project by 3 days, which activties would you crash and by how many days? What is the additional cost of reducing the project by 3 days
|
- What would be the additional cost of completing the project in the minimum time. Indicate which activities would be crashed, by how many days, and their crashing cost.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock