Question: Activity Normal Time (days) Crash Time (days) Normal Cost ($) Crash Cost ($) A 4 3 2000 2600 B 2 1 2200 2800 C 3

Activity

Normal Time (days)

Crash Time (days)

Normal Cost ($)

Crash Cost ($)

A 4 3 2000 2600
B 2 1 2200 2800
C 3 3 500 500
D 8 4 2300 2600
E 6 3 900 1200
F 3 2 3000 4200
G 4 2 1400 200

  1. Identify the critical path. How much time will it take to complete the project?
  1. What is the cost of completing the project in normal time?

  1. If you wished to reduce the project by 3 days, which activties would you crash and by how many days? What is the additional cost of reducing the project by 3 days
  1. What is the minimum time in which the project can be completed?

  1. What would be the additional cost of completing the project in the minimum time. Indicate which activities would be crashed, by how many days, and their crashing cost.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!