Question: ACTIVITY NORMAL TIME (DAYS) CRASH TIME (DAYS) NORMAL COST CRASH COST IMMEDIATE PREDECESSOR(S) Design (A) 7 5 300 350 - Wiring (B) 5 4 900
| ACTIVITY | NORMAL TIME (DAYS) | CRASH TIME (DAYS) | NORMAL COST | CRASH COST | IMMEDIATE PREDECESSOR(S) | ||
| Design (A) | 7 | 5 | 300 | 350 | - | ||
| Wiring (B) | 5 | 4 | 900 | 975 | - | ||
| Chip install (C) | 3 | 2 | 500 | 575 | - | ||
| Software (D) | 4 | 2 | 1,100 | 1,300 | A, B | ||
| Testing (E) | 7 | 4 | 1,200 | 1,650 | C | ||
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?