Question: ACTIVITY NORMAL TIME (DAYS) CRASH TIME (DAYS) NORMAL COST CRASH COST IMMEDIATE PREDECESSOR(S) Design (A) 7 5 300 350 - Wiring (B) 5 4 900

ACTIVITY

NORMAL TIME (DAYS)

CRASH TIME (DAYS)

NORMAL COST

CRASH COST

IMMEDIATE PREDECESSOR(S)

Design (A)

7

5

300

350

-

Wiring (B)

5

4

900

975

-

Chip install (C)

3

2

500

575

-

Software (D)

4

2

1,100

1,300

A, B

Testing (E)

7

4

1,200

1,650

C

What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?