Question: Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 B 4 800 2 2,000
| Activity | Normal Time (days) | Normal Cost ($) | Crash Time (days) | Crash Cost ($) | Immediate Predecessor(s) |
| A | 6 | 1,000 | 5 | 1,200 | |
| B | 4 | 800 | 2 | 2,000 | |
| C | 3 | 600 | 2 | 900 | A, B |
| D | 2 | 1,500 | 1 | 2,000 | B |
| E | 6 | 900 | 4 | 1,200 | C, D |
| F | 2 | 1,300 | 1 | 1,400 | E |
| G | 4 | 900 | 4 | 900 | E |
| H | 4 | 500 | 2 | 900 | G |
- The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in the Table. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14. What would be the least cost to achieve this desired result?
Please complete in excel and not in a notebook.