Question: Activity Normal Time Normal Cost Crash Time Crash Cost Crash Cost Per Day A 3 4 0 2 8 0 4 0 B 2 2

Activity Normal Time Normal Cost Crash Time Crash Cost Crash Cost Per Day
A 34028040
B 22018060
C 220220 N/A
D 430112030
E 31018035
F 125125 N/A
Figure 8-4 Project Crashing Information
Consider the project crashing information presented in Figure 8-4. What is the normal (un-crashed) duration of this project?
a.9 days
b.6 days
c.7 days
d.8 days