Question: Activity Normal Time Normal Cost Maximum Crash Time Crash Cost (per week) A 2 40 1 60 B 4 80 3 25 C 3 100
| Activity | Normal Time | Normal Cost | Maximum Crash Time | Crash Cost (per week) |
|---|---|---|---|---|
| A | 2 | 40 | 1 | 60 |
| B | 4 | 80 | 3 | 25 |
| C | 3 | 100 | 3 | 20 |
| D | 5 | 60 | 1 | 100 |
| E | 2 | 50 | 1 | 40 |
| Total Direct Cost | 330 |
Indirect costs are $55 per week.
Figure: Network Diagram with Duration
Question 8
To reduce the duration of this project, the first activity you would shorten is __________.
Question 9
After this change what is the new total direct cost?
0Question 10
Why did you select this activity to shorten?
Question 11
The second activity you would shorten is _______.
Question 12
For this project, what is the most you would spendper weekto reduce the duration? Why?