Question: Activity Normal Time Normal Cost Maximum Crash Time Crash Cost (per week) A 2 40 1 60 B 4 80 3 25 C 3 100

Activity Normal Time Normal Cost Maximum Crash Time Crash Cost (per week)
A 2 40 1 60
B 4 80 3 25
C 3 100 3 20
D 5 60 1 100
E 2 50 1 40
Total Direct Cost 330

Indirect costs are $55 per week.

Figure: Network Diagram with Duration

Question 8

To reduce the duration of this project, the first activity you would shorten is __________.

Question 9

After this change what is the new total direct cost?

0Question 10

Why did you select this activity to shorten?

Question 11

The second activity you would shorten is _______.

Question 12

For this project, what is the most you would spendper weekto reduce the duration? Why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!