Question: Activity Normal Time Predecessor Normal Cost Crash time Crash Cost A 6 - 1 0 0 3 4 0 0 B 8 - 2 0
Activity Normal Time Predecessor Normal Cost Crash time Crash Cost
A
B
C A
D B
E B
F E
G CD
H F G
Question at position
points
Question at position
Under "normal" conditions what is the earliest the project can be completed?
Under "normal" conditions what is the earliest the project can be completed?
Question at position
points
Question at position
What is the critical path?
What is the critical path?
ACGHF
ACGH
BEFH
BDGH
Question at position
points
Question at position
Suppose you wanted to complete the project one week earlier than under normal conditions. What activityies would you choose to speed up
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
