Question: Activity Normal Time Predecessor Normal Cost Crash time Crash Cost A 6 - 1 0 0 3 4 0 0 B 8 - 2 0

Activity Normal Time Predecessor Normal Cost Crash time Crash Cost
A 6-1003400
B 8-2008200
C 10 A 2002800
D 10 B 100055000
E 9 B 50041000
F 8 E 150064500
G 9 C,D 80051000
H 6 F, G 100041600
Question at position 5
5
3 points
Question at position 5
Under "normal" conditions what is the earliest the project can be completed?
Under "normal" conditions what is the earliest the project can be completed?
27
31
25
33
Question at position 6
6
3 points
Question at position 6
What is the critical path?
What is the critical path?
ACGHF
ACGH
BEFH
BDGH
Question at position 7
7
3 points
Question at position 7
Suppose you wanted to complete the project one week earlier than under normal conditions. What activity(ies) would you choose to speed up.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!