Question: Activity Normal Time (weeks) Minimum Time (weeks) Normal Cost ($) Maximum Cost ($) A 9 6 9,000 15,000 B 6 4 9,000 13,000 C 4

| Activity | Normal Time (weeks) | Minimum Time (weeks) | Normal Cost ($) | Maximum Cost ($) |
| A | 9 | 6 | 9,000 | 15,000 |
| B | 6 | 4 | 9,000 | 13,000 |
| C | 4 | 3 | 10,000 | 12,500 |
| D | 4 | 3 | 8,000 | 11,000 |
| E | 3 | 3 | 7,000 | 7,000 |
| F | 7 | 5 | 17,500 | 24,500 |
| G | 5 | 4 | 5,000 | 6,800 |
| H | 6 | 4 | 8,000 | 11,000 |
44) What is the shortest possible completion time (in weeks) for this project?
10
> 10 and 15
> 15 and 20
> 20
Question 45)
How much will this project cost (in $s) under normal conditions?
50,000
> 50,000 and 75,000
> 75,000 and 100,000
> 100,000
Question 46) What would be the total cost of activity A if this activity is completed in 7 weeks?
10,000
> 10,000 and 11,000
> 11,000 and 12,000
> 12,000 and 13,000
> 13,000
Question 47) What is the cheapest way to reduce the duration of the project by one week from its normal duration?
Reduce activity A by one week
Reduce activity B by one week
Reduce activity C by one week
Reduce activity D by one week
Reduce activity E by one week
Reduce activity F by one week
Reduce activity G by one week
Reduce activity H by one week
A E G Start Finish B D F