Question: Activity Optimistic Most Likely Pessimistic Immediate Predecessor(s) A 7 10 13 Start B 4 8 16 Start C 7 8 9 Start D 1 2
| Activity | Optimistic | Most Likely | Pessimistic | Immediate Predecessor(s) |
| A | 7 | 10 | 13 | Start |
| B | 4 | 8 | 16 | Start |
| C | 7 | 8 | 9 | Start |
| D | 1 | 2 | 4 | B |
| E | 7 | 10 | 11 | A, C |
| F | 4 | 6 | 7 | D, E |
| G | 1 | 3 | 6 | D, E |
| H | 1 | 5 | 7 | F, G |
| I | 1 | 4 | 6 | G |
| J | 3 | 5 | 9 | H |
| K | 3 | 3 | 3 | H |
a) Draw AON diagram showing ES EF, LS and LF; then find how long is the project to take?
b) What is the probability that the project will take more than 37 weeks?
Consider the path A-E-G-H-J. What is the probability that this path will exceed 37 weeks?