Question: Activity Optimistic Most Probable Pessimistic A 4 5 6 B 2.5 3 3.5 C 7 8 9 D 5 5.5 9 E 5 7 9
| Activity | Optimistic | Most Probable | Pessimistic |
| A | 4 | 5 | 6 |
| B | 2.5 | 3 | 3.5 |
| C | 7 | 8 | 9 |
| D | 5 | 5.5 | 9 |
| E | 5 | 7 | 9 |
| F | 2 | 3 | 4 |
| G | 7 | 9 | 11 |
| H | 7 | 8 | 15 |
To help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. The following table lists the activity time estimates (in weeks) for each activity. (See chart attached) Based only on the critical path, what is the estimated probability that the project will be completed within the given time frame? (Round your answers to four decimal places.) (a)Within 21 weeks? B)Within 23 weeks? (c)Within 27 weeks?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts