Question: Activity Optimistic Time ( a ) Most Likely Time ( m ) Pessimistic Time ( b ) Expected Duration A - Review Design 1 8
Activity
Optimistic Time a
Most Likely
Time m
Pessimistic
Time b
Expected Duration
A Review Design
B Assemble Item
C Inspect Item
D Package Item
Figure Duration Estimates
Consider the activity duration estimates presented in Figure Based on the information provided and adopting the PERT conventions to calculate expected activity durations, what is the expected duration of Activity D Package Item
a days
b days
c days
d days