Question: (activity, optimistic time - most likely time - pessimistic time) = notation of the activities *diagram given in that order* Required to find: i) each

(activity, optimistic time - most likely time - pessimistic time) = notation of the activities *diagram given in that order*
Required to find:
i) each path's expected path duration
ii) each path's standard deviation
iii) probability the project can be completed in 44 days or less
iv) probability the project will need more than 49 days to complete