Question: (activity, optimistic time - most likely time - pessimistic time) = notation of the activities *diagram given in that order* Required to find: i) each

 (activity, optimistic time - most likely time - pessimistic time) =

(activity, optimistic time - most likely time - pessimistic time) = notation of the activities *diagram given in that order*

Required to find:

i) each path's expected path duration

ii) each path's standard deviation

iii) probability the project can be completed in 44 days or less

iv) probability the project will need more than 49 days to complete

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!