Question: ACTIVITY OPTIMISTIC TIME PESSIMISTIC TIME MOST LIKELY TIME 1-2 2-3 2-4 3-5 4-5 4-6 5-7 6-7 7-8 7-9 8-10 9-10 1 1 1 3 2
| ACTIVITY | OPTIMISTIC TIME | PESSIMISTIC TIME | MOST LIKELY TIME |
| 1-2 2-3 2-4 3-5 4-5 4-6 5-7 6-7 7-8 7-9 8-10 9-10 | 1 1 1 3 2 3 4 6 2 5 1 3 | 5 3 5 5 4 2 6 8 6 8 3 7 | 1.5 2 3 4 3 5 5 7 4 6 2 5 |
A project has the following characteristics
a) construct the network
b)find the critical path and variance for each event.
c)find the project duration at 95% probability