Question: Activity Optimistic Time (weeks) Most Likely Time (weeks) Pessimistic Time (weeks) Immediate Predecessors A 2 2 6 -- B 2 5 6 -- C 2

Activity Optimistic Time (weeks) Most Likely Time (weeks) Pessimistic Time (weeks) Immediate Predecessors
A 2 2 6 --
B 2 5 6 --
C 2 4 6 A
D 1 3 5 A,B
E 1 2 9 C
F 2 3 6 C
G 3 4 10 D,F
H 1 3 8 E,G

A ) What is the probability that the following project will be completed in 24 weeks or less?

Note

1. In calculating the expected time (te) round to the nearest whole number, and use these rounded numbers for (te) in all subsequent calculations.

2. In calculating the variance, standard deviation, z-value, and probability, round to the nearest second decimal point.

B ) Draw a network diagram on paper. Use the expected time (te) for each task time. Also, in the diagram, indicate earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!