Activity Optomistic Most Likely Pessimistic Critical A 4 6 9 no B 2 3 9
Fantastic news! We've Found the answer you've been seeking!
Question:
Activity | Optomistic | Most Likely | Pessimistic | Critical | |
A | 4 | 6 | 9 | no | |
B | 2 | 3 | 9 | Yes | |
C | 12 | 14 | 15 | YES | |
D | 10 | 28 | 29 | NO | |
E | 3 | 4 | 5 | Yes | |
F | 2 | 4 | 6 | Yes | |
What is the expected Project Completion time? | |||||
What is the standard deviation of project completion time? |