Question: Activity Preceding Duration ES EF LS LF Slack A -- 9 B D, G 11 C A 8 D A 5 E H 3 F

Activity Preceding Duration ES EF LS LF Slack
A -- 9
B D, G 11
C A 8
D A 5
E H 3
F C 12
G A 4
H D 7
I C 7
J B, E, I 6
K F, J 2

Please Complete The ES,EF,LS,LF, and Slack of the chart.