Question: Activity Prede- cessors Duration (days) ES EF LS LF Slack A - 3 B A 7 C A 4 D B,C 5 E C 4

Activity Prede- cessors Duration (days) ES EF LS LF Slack
A - 3
B A 7
C A 4
D B,C 5
E C 4
F D 3
G E 4
H F,G 5

Using the information from the StartFinish sheet, create a resource loading table assuming that each day is 8 hours but you can not have more than 16 hours in one day. Once you completed the first table, move the information to the second table and level the second table so no more than 16 hours per day
Days
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A
B
C
D
E
F
G
H
Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Days
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A
B
C
D
E
F
G
H
Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!