Question: Activity Predecessor A B B D B E C,D F E,A G Optimistic duration 2 2 4 5 1 3 5 Most likely duration 4

Activity Predecessor A B B D B E C,D F E,A G

Activity Predecessor A B B D B E C,D F E,A G Optimistic duration 2 2 4 5 1 3 5 Most likely duration 4 3 5 9 2 4 6 Pessimistic duration 6 7 9 10 3 5 7 Draw the network diagram for the activity list showing above and answer the following questions. 1- What is the total duration of the project? (0.25 grade) 2- What is the critical path of the project? (0.25 grade) 3- What is the total slack for activity C and Activity A? (0.25 grade) 4- What does the total slack for A mean? (0.25 grade)