Question: Activity Predecessor --- A B C D E F G Normal time 4 2 3 1 4 3 2 ws A B D.E If the

Activity Predecessor --- A B C D E F G Normal
Activity Predecessor --- A B C D E F G Normal time 4 2 3 1 4 3 2 ws A B D.E If the duration of activity F is reduced by 2 days, the duration of the project can be reduced by days. (Fill a number in the blank.)