Question: Activity Predecessor Activity F A B C D E FL G H 1 J K L M I K E & B None I &

\begin{tabular}{|l|l|l|} Activity & PredecessorActivity & DurationinDays \\ \hline A & F & 5 \\ \hline B & I & 5 \\ \hline C & K & 4 \\ \hline D & E\& B & 4 \\ \hline E & None & 5 \\ \hline F & I\&L & 2 \\ \hline G & A\& C & 4 \\ \hline H & J & 4 \\ \hline I & None & 2 \\ \hline J & L\& M & 2 \\ \hline K & D \& B & 2 \\ \hline L & None & 5 \\ \hline M & None & 7 \\ \hline \end{tabular} Please draw the network diagram manually on paper, answer questions on the same page, take a picture of your work and upload your file. (If you encounter technical challenges while uploading the file, you may also email your work to the course instructor within the allotted exam time.) Show all your work. Description: a) Given the activities, predecessors, and durations displayed in the precedence table below, draw a network diagram. b) Identify all network diagram pathways and their durations. c) Identify the critical path(s). d) Provide the definition for "critical path" e) How long will it take to complete the project? f) What is the float (slack) time for activity I? g) What is the float (slack) time for activity A ? h) What is the float (slack) time for activity L ? i) What is the float (slack) time for activity H
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts