Question: Activity Predecessor Duration A - 10 B A 4 C A 6 D A 9 E B, C, D 11 F A, E 3 G
Activity Predecessor Duration A - 10 B A 4 C A 6 D A 9 E B, C, D 11 F A, E 3 G F 1
Complete the following steps - ensure each step is completed correctly: 1. Using a blank sheet of paper, create a rough draft of the network diagram using only the letters above to ensure there are no unnecessary crossovers. 2. Create a network diagram using the network methodology and insert the above tasks and durations. 3. Find the duration of the project and critical path by completing a forward and backward pass. 4. Highlight the critical path by circling the tasks that are on the critical path and connect them with a line. 5. Write the duration of the project below the network diagram.