Question: Activity Predecessor Duration (weeks) Crash cost per Week A 6 $200 B 8 $350 A,B 5 $400 D B 4 $150 E 7 $240 F

Activity Predecessor Duration (weeks) Crash cost

Activity Predecessor Duration (weeks) Crash cost per Week A 6 $200 B 8 $350 A,B 5 $400 D B 4 $150 E 7 $240 F C,D 3 $500 G D $175 H E,F,G 5 $320 (9) Find the critical path for this schedule. (a) A-C-E-H (b) A-B-C-E-H (c) B-C-E-H (d) B-D-G-H (10) If we wanted to crash this schedule by 1 week, which task would be shortened first? (a) B (b) C (c) D (d) E