Question: Activity Predecessor Normal Time Crash Time Normal Cost $ Crash Cost $ A - 6 4 500 700 B A 5 4 200 500 C
| Activity | Predecessor | Normal Time | Crash Time | Normal Cost $ | Crash Cost $ |
| A | - | 6 | 4 | 500 | 700 |
| B | A | 5 | 4 | 200 | 500 |
| C | A | 4 | 2 | 600 | 1000 |
| D | B,C | 8 | 5 | 750 | 1500 |
1. which activity has the largest total allowable crash time?
2. What is the total cost of the project on normal time? = $
3. If activity c were to crash to the max, what would be the total crash cost for this activity?