Question: Activity Predecessor Normal Time Crash Time Normal Cost $ Crash Cost $ A - 6 4 500 700 B A 5 4 200 500 C

Activity

Predecessor

Normal Time

Crash Time

Normal Cost $

Crash Cost $

A

-

6

4

500

700

B

A

5

4

200

500

C

A

4

2

600

1000

D

B,C

8

5

750

1500

1. which activity has the largest total allowable crash time?

2. What is the total cost of the project on normal time? = $

3. If activity c were to crash to the max, what would be the total crash cost for this activity?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!