Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost / day A - 5 $ 5 0 0 3 $ 1 ,

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost/day
A -5 $5003 $1,500 $500
B -4 $4002 $2,000 $800
C B 7 $7006 $1,600 $900
D A, C 2 $2001 $500 $300
E A, C 3 $300---
F B 8 $8005 $2,900 $700
G D 5 $5004 $1,000 $500
H E, F 6 $6003 $1,800 $400Part E: Compress the schedule by TWO more days. Each crash should reduce the completion time by 1 day. Show your work in the table.
Path 3rd Crash 4th Crash
BCEH
BFH
ADG
BCDG
AEH
Activity(ies) Crashed
Crash Cost
Direct Cost
Indirect Cost
Total Cost