Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost / day A - 5 $ 5 0 0 3 $ 1 ,
Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash costday
A $ $ $
B $ $ $
C B $ $ $
D A C $ $ $
E A C $
F B $ $ $
G D $ $ $
H E F $ $ $Part E: Compress the schedule by TWO more days. Each crash should reduce the completion time by day. Show your work in the table.
Path rd Crash th Crash
BCEH
BFH
ADG
BCDG
AEH
Activityies Crashed
Crash Cost
Direct Cost
Indirect Cost
Total Cost
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
