Question: Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost / day Max Crash A - 5 $ 5 0 0 3 $

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost Crash cost/day Max Crash
A -5 $5003 $1,500 $5002
B -4 $4002 $2,000 $8002
C B 7 $7006 $1,600 $9001
D A, C 2 $2001 $500 $3001
E A, C 3 $300----
F B 8 $8005 $2,900 $7003
G D 5 $5004 $1,000 $5001
H E, F 6 $6003 $1,800 $4003 The total cost of finishing the project 3 days sooner is __________ Dollars.