Question: Activity Predecessor Normal time (weeks) Minimum time (weeks) Normal Cost (euros) Maximum Cost (euros) A 2 1 10,000 15,000 B 4 4 2,000 2,000 A,B

Activity Predecessor Normal time (weeks) Minimum
Activity Predecessor Normal time (weeks) Minimum
Activity Predecessor Normal time (weeks) Minimum time (weeks) Normal Cost (euros) Maximum Cost (euros) A 2 1 10,000 15,000 B 4 4 2,000 2,000 A,B 6 5 5,000 10,000 D A 3 3 20,000 20,000 E 5 5 10,000 10,000 F D 5 5 7,000 7,000 G F, E 6 6 10,000 10,000 H 3 1 3,000 5,000 - G 3 4,000 N 6,000 J H, 5 5 8,000 8,000 5) Reduce the project duration in one week, giving two options with the associated cost of each one