Question: Activity Predecessor Optimistic Most Likely Pessimistic A - - 9 1 5 2 1 B - - 1 3 2 1 2 3 C A

Activity Predecessor Optimistic Most Likely Pessimistic
A --91521
B --132123
C A 6918
D A 233547
E B 192627
F C 232941
G D, E 142026
H F, G 258
Refer to the table above to answer the question that follows