Question: Activity Predecessor Time A - 4 B A 5 C B, E 7 D - 9 E D 3 F E 6 G C,F 2

Activity

Predecessor

Time

A

-

4

B

A

5

C

B, E

7

D

-

9

E

D

3

F

E

6

G

C,F

2

please draw a network diagram to help you find the following information (only provide numberical values when asked, except for critical path. Critical path please express in the follow way: a-b-c OR abc OR a,b,c

a). the earliest finish (EF) time for activity C is: days.

b). the critical path for the project is

c). what is the completion time of the project? days.

d). what is the slack on activity B? days

e). what is the late start (LS) on activity F?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!