Question: Activity Predecessors Optimistic Time ( a ) Most likely Time ( m ) Pessimistic Time ( b ) A - - - - - -

Activity Predecessors
Optimistic
Time (a) Most likely
Time (m) Pessimistic
Time (b)
A -------345
B A 234
C A 456
D B 444
E B 256
F C, D, E 245
G F 246
H F 467
I G, H 468
NB: Time periods are in years
a. Draw the activity network for this problem (either AON or AOA).
b. Determine the expected time and variance for each activity.
c. Show the activity schedule (ES, EF, LS, LF) as well as the slack. You may work in the network or show the results in a table.
d. Determine the state of the critical path for this project. This must be based on your work at C., and not by inspection.
e. What is the expected time, variance and standard deviation of the project?
f. What is the probability that the project will be finished within 30 day

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!