Question: Activity Predecessors ti mes (da ys) a m b A .... 4 6 8 B A 4 6 8 C A 2 4 6 D
| Activity | Predecessors | ti | mes (da | ys) |
|---|---|---|---|---|
| a | m | b | ||
| A | .... | 4 | 6 | 8 |
| B | A | 4 | 6 | 8 |
| C | A | 2 | 4 | 6 |
| D | B,C | 1 | 8 | 9 |
| E | D | 3 | 5 | 7 |
| F | D,E | 2 | 3 | 4 |
1. The critical path is?
2. Slack time exists for activity ___?
3. The late start time for activity C is ___?
4. The expected time for project completion is?
5. What is the probability of completing this project within 25 days?